Permits

Grading Permits: Cut and Fill in Austin and Los Angeles

6 min · Updated 2026-09-28

When moving soil in a yard needs a grading permit in Los Angeles, Austin's 4-foot limit on cut and fill, and the exceptions for foundations and pools.

Written by DueRivaLast reviewed: 2026-09-28Review standard

Moving soil on a lot, cutting it away or filling it in, is grading, and each city draws its own line. Los Angeles requires a grading permit from its Department of Building and Safety to grade a yard or to bring soil onto or haul it off a site, with exceptions. Small jobs are among them: a cut less than 2 feet deep, or one that leaves no cut slope over 5 feet high and steeper than 1 vertical in 2 horizontal, or a fill less than 1 foot deep on natural ground flatter than 1 in 10, each only up to 50 cubic yards and only if the lot’s drainage is unchanged. Digging for a foundation or pool under a building permit, outside hillside areas, is also excepted. Austin’s environment code limits cut and fill on a tract to 4 feet of depth, with exceptions that include the city’s urban watersheds and the digging for a building’s foundation or a swimming pool; this guide has not found a separate Austin grading permit, so ask Development Services what permit covers the work.

Grading lines in Austin and Los Angeles
RuleAustinLos Angeles
PermitAsk Development Services; building or altering four or fewer homes on a legal lot with four or fewer units needs no site plan outside the 100-year floodplain, but may still need a building permitA grading permit for grading or moving soil to or from the site, unless an exception applies
CutNo deeper than 4 ft, except in urban watersheds, for a foundation or pool, and other listed casesNo permit under 2 ft deep, or leaving no cut slope over 5 ft high and steeper than 1 in 2; up to 50 cu yd, drainage unchanged
FillNo deeper than 4 ft, except in urban watersheds, under a foundation with sides perpendicular to the ground or pier and beam, and other listed cases. A fill area must be restored and stabilizedNo permit under 1 ft deep on natural ground flatter than 1 in 10; up to 50 cu yd, drainage unchanged
Foundations and poolsCut for a foundation or pool, and fill under a foundation with sides perpendicular to the ground or pier and beam, are excepted from the 4 ft limitNo grading permit for excavations for footings, basements or pools under a valid building permit, outside hillside areas

Los Angeles: when grading needs a permit

No one may grade, or bring earth onto or take it off a site, without a grading permit from the Department of Building and Safety, and in hillside areas a copy of the permit has to be at the site. The code’s other provisions still apply, but no permit is needed for an excavation less than 2 feet deep, or one that does not create a cut slope more than 5 feet high and steeper than 1 vertical in 2 horizontal, unless the cut exceeds 50 cubic yards or changes the existing drainage; for a fill less than 1 foot deep on natural terrain flatter than 1 in 10, unless it exceeds 50 cubic yards or changes the drainage; for excavations outside hillside areas for basements, footings, piles, swimming pools or underground structures a valid building permit authorizes; or for excavations for wells, tunnels or utilities that do not provide vertical or lateral support for buildings or harm the safety or stability of private or public property. Grading of more than 100 cubic yards with an excavation deeper than 5 feet has to be done by a California-licensed contractor. The retaining wall permit brief covers the walls that often come with a cut.

Austin: the 4-foot limit on cut and fill

Austin’s environment code, in its requirements for all watersheds, says cuts on a tract may not exceed 4 feet of depth, and fill may not exceed 4 feet, and that a fill area must be restored and stabilized. The exceptions include the urban watersheds (among them Boggy, Blunn, Johnson, Little Walnut, Shoal, Waller and the East and West Bouldin creek watersheds, and parts of the Colorado River watershed), a roadway right-of-way, cut for a building foundation or a swimming pool, fill under a foundation with sides perpendicular to the ground or under pier and beam construction, utility work and wastewater drain fields (a cut for them must be restored to natural grade), and a driveway needed for primary access, up to 8 feet under conditions that include no other feasible location. A site plan is not required for building or altering four or fewer homes on a legal lot with four or fewer units outside the 100-year floodplain, or inside it where the effect on the waterway is insignificant (ask Development Services), but the exemption does not waive a building permit. The code read for this guide does not say whether grading alone needs a site plan, so ask Development Services. Austin Energy’s criteria also say final grades in its easements should not be changed without its written approval, and the drainage code bars placing an obstruction in a waterway, which includes the 100-year and 25-year floodplains, unless an approved development application authorizes it; the easements guide covers both.

Before any digging, call 811; the before-you-dig guide explains how. Elsewhere, ask the city or county building department whether grading on your lot needs a permit.

Primary sources

What this page was checked against

  • Los Angeles Municipal Code, Sec. 91.106.1.2: Grading permits

    City of Los Angeles · checked 2026-09-28

    Used for: A grading permit to grade or to import or export earth, a copy at hillside sites; a California-licensed contractor for more than 100 cu yd with an excavation over 5 ft deep; the five exceptions: a cut under 2 ft deep or leaving no cut slope over 5 ft high and steeper than 1 in 2, or a fill under 1 ft on terrain flatter than 1 in 10, each up to 50 cu yd with drainage unchanged; hillside caissons and piles; non-hillside foundation and pool excavations under a valid building permit; wells, tunnels and utilities that give no support and harm no property (Ord. No. 172,592, operative 7/1/99).

  • Austin City Code, §§ 25-8-341 and 25-8-342: Cut and fill requirements

    City of Austin · checked 2026-09-28

    Used for: In all watersheds, cut and fill on a tract no more than 4 ft deep, a fill area restored and stabilized, with exceptions: urban watersheds (25-8-1), roadway rights-of-way, cut for a foundation or pool, fill under a foundation with perpendicular sides or pier and beam, utilities and drain fields, water quality facilities, trails and a primary-access driveway up to 8 ft under conditions.

  • Austin City Code, § 25-5-2: Site plan exemptions

    City of Austin · checked 2026-09-28

    Used for: No site plan for building or altering four or fewer residential units on a legal lot with four or fewer units, outside the 100-year floodplain or with an insignificant effect on the waterway; an exemption does not waive building permit requirements.

  • Utilities Criteria Manual, Section 1.10.0: Clearance and safety requirements

    Austin Energy, City of Austin · checked 2026-09-28

    Used for: Final grades in its easements should not be changed without its prior written approval (1.10.10.1).

  • Austin City Code, Chapter 25-7: Drainage

    City of Austin · checked 2026-09-28

    Used for: No obstruction in a waterway, its 100-year and 25-year floodplains included, unless an approved development application allows it (25-7-2, 25-7-3).